KB
Sign InImporting Projects and Portfolios
How to Import Projects
Only a project name is required to import, other properties are optional but include: description, start date, status, portfolio, customer organization, target due date and agile points. If you have data that does not easily map to default fields, create a custom field before importing. (More on Custom Fields)
Note: If you do not include a customer organization or portfolio this will need to be updated manually.
Step 1: Click Tools on the top bar
Step 2: Select Import
Step 3: Select Projects
Step 4: Upload the csv file you wish to import.
Step 5: Map the columns to the appropriate fields. A project name is the minimum needed to import. If the default fields do not fit your data, you can create custom fields before importing. When finished mapping, click import.
Step 6: You are now done importing. You may close the notification window and the import will continue in the background while you work. It may take a few minutes to complete the import.
How to Import Portfolios
CSV files accepted.
Only a portfolio name is required to import, other properties are optional but include: description and parent portfolio.
Step 1: Click Tools on the top bar.
Step 2: Select Import.
Step 3: Select Portfolios
Step 4: Upload the csv file you wish to import.
Step 5: Map the columns to the appropriate fields. A portfolio name is the minimum needed to import. When finished mapping, click import.
Step 6: You are now done importing. You may close the notification window and the import will continue in the background while you work. It may take a few minutes to complete the import.